SYSCON understands what it takes to see a major construction project to completion. One of the most vital aspects of any successful project is expert planning and preconstruction. SYSCON understands what it takes to see a major construction project to completion. One of the most vital aspects of any successful project is expert planning and preconstruction. SYSCON understands what it takes to see a major construction project to completion. One of the most vital aspects of any successful project is expert planning and preconstruction.
Project Scope Details
DESIGN
SSOE
GENERAL CONTRACTOR
SYSCON
MAIN SUBCONRTRACTOR
LOT AREA
52.48 ACRES
CONSTRUCTION AREA

MAIN PLANT 100,332 SF

OFFICE 20,714 SF

TOTAL 121,046 SF

Floors

MAIN PLANT: 33 FT HIGH

BUILDING STRUCTURES

S/STRUCTURES

WALL METAL PANEL (2”)

TPO (3”) ROOFING

MAJOR ACTIVITIES

FULL TURN-KEY: CIVIL, ARCH, ELEC & MECH WORK

Project Scope Details
GENERAL CONTRACTOR
SYSCON
MAIN SUBCONTRACTOR
LOT AREA
52.48 ACRES
CONSTRUCTION AREA
121,046 SQ FT
Project Scope Details
LOT AREA
This is some text inside of a div block.
CONSTRUCTION AREA
This is some text inside of a div block.
ELEVATION
This is some text inside of a div block.
BUILDING STRUCTURES
This is some text inside of a div block.
MAJOR ACTIVITES
This is some text inside of a div block.
DESIGN
This is some text inside of a div block.
FLOORS
MAIN PLANT: 33’
BUILDING STRUCTURES
S/STRUCTURES + WALL METAL PANEL (2”) + TPO (3”) ROOFING
MAJOR ACTIVITES
FULL TURN-KEY: CIVIL, ARCH, ELEC & MECH WORK